Central Middle School:
- Continuing
metal panel install on the exterior, but building is enclosed and dry
- · Drywall
complete classroom wing all 3 floors. Finishes ongoing.
- · Drywall
in other sections almost complete, finish painting has started in some areas
- · MEP rough-in almost complete, MEP Finishes have started
West Middle School Renovations:
- Phase 3: Woodshop, Digital Design, Art, Music, Choir & Orchestra are all moved and functioning in their new spaces.
- Phase 4: Science Room remodel, East (Old Art) was partitioned off over break, demolition ongoing.
- Phase 1: Former pool renovation to gymnasium: Ceilings and paint complete. Floor slab prepped. Bathroom fixtures and partitions, entryway drywall, ceilings, flooring, finish paint on going.
North Middle School
- Punch list work over break almost complete.
- Sound Attenuation panels (Tectum), Science room ceilings complete over break.
- Did not get all the walls or the STEAM area due to manpower issues.
Northern High School Natatorium
- Block ongoing, precast seating planks were set last week.
Northern Athletic Event Facility
- Changes and fencing changes made
Central Athletic Event Facility
- Punchlist,
water issues, Sod, misc. grading: spring or as weather permits.